Tuttle Enterprises is considering a project that has the following cash flow and required return data. What is the project's NPV? Note that if a project's projected NPV is negative, it should be rejected. Required Return: 11.00%
Year 0 1 2 3 4
Cash flows -$1,000 $350 $350 $350 $350