Assume that a U.S. firm plans to invest £200 million for a project in U.K., and the firm estimates the following values: the value of an unlevered project (Vu) = £150 million and PV(financing side effects) = £75 million. Find the present value of this project by using the Adjusted Present Value (APV) formula.