Find out earliest completion time and critical path


Given following information about staging the community play on Independence Day.

(a) Make a PDM or CPM diagram.

(b) Find out the earliest completion time for play and critical path

(c) Based upon the critical path, what completion date are you 80% confident of achieving? 40% confident?

(d) Will a 1-day delay in this project be serious?

    Time (days)
Activity Predecessor a m b
1 - 2 4 6
2 - 5 5 5
3 2 3 5 7
4 1 7 10 13
5 1 11 12 13
6 2,4 5 6 7
7 3 9 10 11
8 3,6 5 7 9
9 4 7 9 11
10 5 3 3 3
11 7 15 17 19
12 8 6 8 10
13 9,10 7 8 15
14 7 12 14 16

Request for Solution File

Ask an Expert for Answer!!
Basic Statistics: Find out earliest completion time and critical path
Reference No:- TGS022772

Expected delivery within 24 Hours