Find out completion time and standard deviation


Consider following table:

  PRET. ACT TIME  ESTIMATES ;(days)
Activity   to   tml   tp   te
A - 2 3 4  
B - 2 4 6  
C - 2 4 6  
D A 3 4 5  
E B 2 5 8  
F C 2 4 6  
G D,E,F 1 2 3  
  1. Find out the completion time and standard deviation (σ) for project- round off standard deviation to the nearest hundredth: two decimal places
  2. Find out the completion time at 95% confidence level?