Your program has an RDT&E-funded project scheduled to start in July 2015 which is expected to take 12 months to complete. The project is expected to cost a total of $12 million (then-year dollars), with cost expected to be incurred at a rate of $1 million per month. Which of the following is the appropriate budget request for this project?