Baseballs (z1) requires 3 minutes/unit for cutting and 2 minutes/unit for glueing. Basketballs (z2) requires 2 minutes/unit for cutting and 4 minutes/unit for glueing. 600 minutes are available for cutting, and 600 minutes for glueing. Both have $1.50/unit contributions. Objective Function? Contraints?