The Kraig Corporation manufactures custom-made purses. The following data pertains to Job XY5:
Direct materials placed into production $4,000
Direct labor hours worked 50 hours
Direct labor rate per hour $ 15
Machine hours worked 100 hours
Factory overhead is applied using a plant-wide rate based on direct labor hours. Factory overhead was budgeted at $60,000 for the year and the direct labor hours were estimated to be 15,000. Job XY5 consists of 50 units. What is overhead cost assigned to Job XY5?
$200
$400
$750
$1,500