When estimating resource needs, project teams should consider all the following EXCEPT:
|
support needs such as information systems.
|
|
the time required to communicate between activities.
|
|
specific knowledge or skills that are required.
|
|
scoring models.
|
A common tool project teams use is a responsibility assignment matrix (RAM). Typically, this chart will depict:
|
the date each activity will begin.
|
|
the duration of each activity.
|
|
the roles key members of the team will play on each activity.
|
|
organizational reporting structure
|
Faced with significant schedule challenges, the project manager has several responsibilities. All of the following are among the project manager's responsibilities EXCEPT:
|
willingly accept end dates dictated by customers or sponsors
|
|
persuade all stakeholders that the schedule makes sense
|
|
deliver the project according to the agreed-upon schedule
|
|
determine a schedule that is possible to achieve
|