1. Show and explain why critical average and max average rules both generate a risk measure of 64.65 for the node labeled Network Operations Capability portfolio.
2. Suppose the Figure 2 presents a portion of a capability portfolio defined as part of engineering an enterprise system. Given the information shown, apply the risk analysis algebra in Module 6 to derive a risk measure for Capability 2. What risks are driving this measure?