Explain TWO strategies that a project manager might implement to address a project risk.
Risk avoidance - this strategy would be 'exiting the method that is giving rise to the risk'. This would mean aborting the entire project or changing or abandoning particular goals or objectives of the project.
Risk transference - subcontract the risk to a third party like as a specialist supplier who is more experienced in handling the risk. Insurance is another method to use to transmit some elements of risk.