1. Calculate the latest start for Task D if one of its successors, task F, has a latest start on day, 12, its other successor, task, has a latest start on day 12, and the duration of Task D is 2 days.
2. Explain resource loading and resource leveling, and how they differ. Give examples. type it out.
3. Identify the key factors that need to be considered when setting up a monitoring system. What factors are difficult to monitor? What are the benefits of timely, appropriate, detailed information? Type it out.