Sample 1 2 3 4 5 Xbar R
1 1.55 1.58 1.64 1.67 1.50 1.588 0.17
2 1.52 1.62 1.71 1.74 1.60
3 1.47 1.57 1.44 1.56 1.42
4 1.67 1.73 1.76 1.64 1.64
5 1.46 1.52 1.60 1.41 1.43
6 1.44 1.50 1.53 1.37 1.41
7 1.55 1.64 1.70 1.53 1.58
8 1.54 1.72 1.66 1.52 1.57
9 1.48 1.60 1.57 1.46 1.51
10 1.43 1.55 1.52 1.43 1.46
11 1.40 1.52 1.56 1.38 1.43
12 1.60 1.44 1.55 1.58 1.49
13 1.48 1.46 1.57 1.60 1.65
14 1.56 1.54 1.65 1.68 1.59
15 1.42 1.39 1.51 1.54 1.45
16 1.70 1.71 1.61 1.73 1.64
17 1.51 1.35 1.37 1.49 1.40
18 1.41 1.32 1.44 1.32 1.35
19 1.69 1.58 1.75 1.60 1.63
20 1.67 1.56 1.79 1.58 1.61
21 1.65 1.57 1.68 1.56 1.59
22 1.52 1.46 1.55 1.45 1.46
23 1.51 1.41 1.54 1.42 1.45
24 1.62 1.51 1.69 1.53 1.56
25 1.57 1.46 1.60 1.47 1.51
Q1. First plot the data using Excel.
Q2. Then determine the UCL and LCL. Do any of the data points need to be thrown out? If so, then recalculate the UCL and LCL.
Q3. Then you begin to plot results on this chart. Here are the next 6 samples of data (sample size = 5).
Sample # 1 2 3 4 5 Xbar
26 1.51 1.35 1.37 1.49 1.40
27 1.41 1.32 1.44 1.32 1.35
28 1.69 1.58 1.72 1.60 1.63
29 1.67 1.56 1.70 1.58 1.61
30 1.65 1.57 1.68 1.56 1.59
31 1.52 1.46 1.55 1.45 1.46
Plot these on the control chart.
Q4. Is the process in control?