Explain how you would estimate the project management activity.
Project management:
This effort is dependent onto two things as whether a full-time project manager is to be utilized or not and the in general expected period of the project. When a full-time manager is needed, in that case one simply multiplies the duration of the project with four to acquire the number of days' effort included (notice the main text for a discussion of why only four days a week is accessible for every person over the long run). When a half-time project manager is to be used, after that the number of weeks is multiplied with two and so on.