1. Explain how you would determine appropriate objectives and trade-o for this project and how might you employ a weighting method to assist with this task.
2. How might use of swot analysis play a role.
3. What role might benchmarking play.
4. Assume that the network for this project is provided in figure2 on the second page. Also assume that it is not possible to accomplish tasks a,d, and e any faster than the durations provided on the second page. what other data would be needed in order to determine if project crashing can occur.
5. If we now add in the assumption that activity d and activity f require the same person (resource) then we are faced with an example of resource leveling. either d or f must be delayed. how would we determine which resource leveling option is preferred?