An aircraft repair facility currently has four jobs awaiting work. Four teams of mechanics are available. Each team can work on only one of the jobs. Over a period of several months the manager has evaluated the repair teams in a variety of jobs. Evaluations are based on 100 being the maximum evaluation possible. The teams and their ratings for the available jobs are given in the table below. Based on these ratings determine the assignment of teams to jobs that will maximize the overall rating.
Team Job1
|
|
2
|
3
|
4
|
O-420 overhaul
|
40
|
60
|
80
|
50
|
Landing gear strut repair
|
30
|
70
|
40
|
80
|
Control system overhaul
|
80
|
90
|
80
|
70
|
Hydraulic system repair
|
20
|
50
|
30
|
40
|