Evaluating a suppliers cost and schedule data


Question: What functional specialist is responsible for reviewing and evaluating a supplier's cost and schedule data to determine whether systems design, production, integration, and test events will meet contractual requirements? a. Engineering Specialist b. Contract Administration Specialist c. Quality Assurance Specialist d. Earned Value Management Specialist