Problem: Kimberly is the project manager on a five-year construction project. Risk analysis is critical due to the duration and complexity of the project. She decides to run a sensitivity analysis to evaluate the potential impact of risks on the schedule. This simulation generates a Tornado diagram that displays: (For Ref Only, Question #: PM-02257) Group of answer choices Threshold for organizational risk tolerance based on probability and impact Overall probability of meeting the project schedule and target end date Feedback loops on the critical path with high criticality indexes Risk factors in descending order of positive or negative correlation to the schedule