Phil would like to consider the costs that his accountants are currently using for inventory carrying and setup for the gear boxes and input shafts. the costs are as follows:part cost gear box setup=$90/order inventory carrying cost=$2unit/week. Input shaft setup=$45 order. inventory carrying cost=$1unit/week Given the cost structure, evaluate the cost of the schedule. assume inventory is valued at the end of each week.