Q1. Why the critical path is the longest path in the network diagram? Explain.
Q2. Why the critical path is shortest duration in which the project can be completed? Explain.
Q3. Explain how to use forward pass to estimate project completion time.
Q4. Explain how to use backward pass to identify critical and noncritical activities.