Question 1: An advertising project manager developed the network diagram shown below for a new advertising campaign. In addition, the manager gathered the time information for each activity, as shown in the below table.
Estimate the probability that the noncritical path B-F-G will take more than 20 weeks. Hint: Subtract from 1.0 the probability that B-F-G will take less than 20 weeks.