Find the schedules and costs variances for a project that has an actual cost at month 22 of $540,000 a scheduled cost of $523,000 and earned values of $535,000

A software development project at day 70 exhibits an actual cost of $78,000 and a schedule cost of $84,000. The software manager estimates a value completed of $81,000. What are the cost and schedule variances and CSI? Estimate the time variance.