Estimate the schedule and cost


A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000.

Request for Solution File

Ask an Expert for Answer!!
Basic Computer Science: Estimate the schedule and cost
Reference No:- TGS01396058

Expected delivery within 24 Hours