Estimate the hourly production in bank measures


Problem: Estimate the hourly production in bank measures of a hydraulic shovel loading sand and gravel into trucks. The machine is equipped with a bottom dump bucket having a heaped bucket capacity of 5.2 Lm3. Average swing angle is 60 degrees. The bucket fill factor is 0.95, job efficiency is 0.69, and load factor is 0.89.