Estimate the expected capital costs of the generation


It has been estimated that a 400 MW expansion of the existing SEGS solar plant in California would cost $2.4 billion. Estimate the expected capital costs of the generation facility in dollars/kW capacity and the minimum cost of electricity per kWh generated by the addition, if they are operated at full capacity for 6 h/day and have a lifetime of 30 years.