Estimate the costs for the resources and add the costs to


CMGT Project Task List

The project for the company offsite 2-day training session has been given a preliminary go-ahead. However, a budget needs to be submitted for approval.

Update the Microsoft Project file submitted in Week Two by adding the following information:

• Identify resources (both personnel and materiel) needed for the project.
• Assign the resources to the project tasks.
• Estimate the costs for the resources, and add the costs to the resource information in the Microsoft Project file.
• Estimate the total cost for the project, using the Microsoft Project budget or cost reports.

Solution Preview :

Prepared by a verified Expert
Management Information Sys: Estimate the costs for the resources and add the costs to
Reference No:- TGS01715511

Now Priced at $35 (50% Discount)

Recommended (99%)

Rated (4.3/5)