Methods of Estimating Costs: Multiple Regression
Multiple regression results from the data of Adriana Corporation are as follows:
Equation: Overhead = $124,570 + ($31.93 × Labor-hours) + ($41.10 × Machine-hours) Statistical data
|
|
Correlation coefficient
|
.982
|
R 2
|
.964
|
Required
Estimate overhead using the multiple regression results, assuming that the company expects the plant to operate at a monthly average of 9,000 machine-hours and 3,000 labor-hours next year.