Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this Project:
a. Draw the network
b. Estimate earliest start and earliest finish times along with latest start and latest finish times.
c. What is the critical path?
d. What are the slack times for activities B and F?
e. What is the probability that the project will be completed in 18 days or less