Eric? Krassow's firm is about to bid on a new radar system. Although the product uses new? technology, Krassow believes that a learning rate of 85% is appropriate. The first unit is expected to take 760 hours, and the contract is for 13 units.
a) The total amount of hours to build the 13 units = ______ hours?
b) The average time to build each of the 13 units = _______ hours?
c) Worker work 2,080 hours per year, the number of workers required to complete this contract in a year = ____ workers?