Engineering design - design report - evaluation - the


EVALUATION - THE WEIGHTED OBJECTIVE METHOD

ASSESSMENT QUESTION

We intend to use the weighted objective method to select a family car. There are four cars to choose from, with the following characteristics:

Model

Slobmobile

Cheapo

GT

Guzzler

Fuel Consumption (mpg)

25

50

30

15

Initial Cost (f)

25,000

6,000

15,000

18,000

Reliability

(% with faults)

4

 

8

5

Acceleration time from 0 to 60 mph (sec)

15

1 N

7

12

It can be assumed that all of the vehicles meet the normal safety regulations and satisfy mandatory aspects of the design brief. Carry out a weighted objective analysis to select the car that you would most like to own. A blank weighted objective chart is provided for you to fill in.

1. Rank objectives in order and determine weightings.

2. Devise a scoring system for each objective.

3. Calculate scores and weighted scores for each car, determine best choice.

Solution Preview :

Prepared by a verified Expert
Other Engineering: Engineering design - design report - evaluation - the
Reference No:- TGS02873591

Now Priced at $50 (50% Discount)

Recommended (99%)

Rated (4.3/5)