Question: Embassy Club Condominium, located on the west coast of Florida, is undetaking a summer renovation of tis main building. The project is scheduled to begin May 1, and a September 1 (17 week) completion date is desired. The condominium manager identified the following renovation activites and their estimated times.
Activity |
Immediate Predecessor |
Time |
A |
|
3 |
B |
|
1 |
C |
|
2 |
D |
A,B,C |
4 |
E |
C,D |
5 |
F |
A |
3 |
G |
D,F |
6 |
H |
E |
4 |
a) Draw a project network.
b) What are the critical activities?
c) What activity has the most slack time?
d) Will the project be completed by September 1?