Problem:
An equal tangent vertical curve connects a 1% and 3% initial and final grade. Design speed is 70mi/h. The high point is at 822ft. If the PVC is at station 110+00.
Required:
Question: What is the elevation at the curve at station 112+22?
Note: Explain the solution in detail.