Problem:
An equal tangent vertical curve connects a 1% and 3% initial and final grade. Design speed is 70mi/h. The high point is at 822ft.
Required:
Question: If the PVC is at station 110+00, what is the elevation at the curve at station 112+22?
Note: Provide support for your rationale.