Earned value analysis complete the earned value analysis


Earned Value Analysis Complete the earned value analysis for the following project. In this project, you are building a treehouse that consists of five segments. You plan that the project will take a total of 10 days to complete, and you budget $100 per day to complete the five segments (HINT: It is suggested that you use each side to represent 200 PV. In other words, you should plan to complete one side every two days, for a scheduled PV of 100 per day). After five days, you have the following information regarding completion of the project. Day1: Side 1 25% completed, spent $75 Day2: Side 1 completed, side 2 65% completed, spent $180 Day3: Side 2 completed, side 3 45% completed, spent $145 Day 4: Side 3 completed, spent $100 Day 5: Side 4 20% completed, spent $60 1. Calculate the following EV parameters: PV EV AC BAC CV SV EAC ETC 2. Using your knowledge of EV, interpret the status of this project. You do NOT need to graph the project.

Request for Solution File

Ask an Expert for Answer!!
Financial Management: Earned value analysis complete the earned value analysis
Reference No:- TGS02371577

Expected delivery within 24 Hours