Earned Value Analysis Complete the earned value analysis for the following project. In this project, you are building a treehouse that consists of five segments. You plan that the project will take a total of 10 days to complete, and you budget $100 per day to complete the five segments (HINT: It is suggested that you use each side to represent 200 PV. In other words, you should plan to complete one side every two days, for a scheduled PV of 100 per day). After five days, you have the following information regarding completion of the project. Day1: Side 1 25% completed, spent $75 Day2: Side 1 completed, side 2 65% completed, spent $180 Day3: Side 2 completed, side 3 45% completed, spent $145 Day 4: Side 3 completed, spent $100 Day 5: Side 4 20% completed, spent $60 1. Calculate the following EV parameters: PV EV AC BAC CV SV EAC ETC 2. Using your knowledge of EV, interpret the status of this project. You do NOT need to graph the project.