Your earned value analysis calculates, "The PV was $1,700, the EV is $1,850, and the AC is $2,100, so we have a CV of $-250 and an SV of $150." So you tell your boss exactly that. What does the above tell you about this project, and how would you tell the boss? What else do you need to know and what actions might you take next?