Earned value analysis


Problem:

You are the project manager for creating a new printer driver.  There are four modules in the driver.  Each module is to take one day and is budgeted for $1,000 per module.  The modules are scheduled to be completed sequentially.  Today is the end of day 3 and your senior management has asked for a progress report.

Using the project status chart below, calculate the values required and provide a verbal interpretation of what the answer means.

TASK

DAY 1

DAY 2

DAY 3

DAY 4

STATUS AT END OF DAY 3

Module 1

S--F

 

 

 

Complete, spent $1,000

Module 2

 

S--PF

--F

 

Complete, spent $1,200

Module 3

 

 

PS-S-PF

 

Half done, spent $600

Module 4

 

 

 

PS-PF

Not yet started


S – Start                   
F – Finish                   
PS – Planned Start                   
PF – Planned Finish     

WHAT IS:

CALCULATION

ANSWER

INTERPRETATION OF THE ANSWER

BCWS

1,000 + 1,000 + 1,000

3,000

We should have done $3000 worth of work.

BCWP

2,800 / 3,000

93%

93% of the work IS done on the current budgeted basis.

ACWP

1,000 + 1,200 + 600

2,800

We have done $2800 worth of work.

BAC

1,000 + 1,000 + 1,000 + 1,000

4,000

We budgeted $4,000 for the total job.

CV

BCWP - ACWP

93% - 2,800

2,799.07

NEGATIVE is over budget, POSITIVE is under budget.

CPI

BCWP / ACWP

93% / 2,800

.033

We are getting .033 cents out of every $1.

SV

BCWP - BCWS

93% - 3,000

2,999.07

NEGATIVE is behind schedule, POSITIVE is ahead of schedule.

SPI

BCWP / BCWS

93% / 3,000

.031

We are progressing at .031% of the rate originally planned.

EAC

1,000 + 1,200 + 600 + 600 + 1,200

4,600

We expect the TOTAL project to cost $4,600.

ETC

600 + 1,200

1,800

From this point on, we expect the project to cost $1,800 more to finish.

VAC

4,600 - 4,000

600

We are currently around $600 under budget.

              
Given the previous, how complete is the project?  Give three answers based on the three rules presented in the slide below.

A project manager can adopt one of the following rules for a project to report percent complete:

50/50 Rule — A task is 50% complete when It begins and gets credit for the last 50% only when it Is completed.

20/80 Rule — A task is considered 20% complete when it begins and gets credit for the last 80% only when it is completed.

0/100 Rule — A task does not get credit for partial completion, only full completion.

Solution Preview :

Prepared by a verified Expert
Other Management: Earned value analysis
Reference No:- TGS02006296

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)