What is the earliest completion time for a project with this information about activities
Activity
|
Optimistic Time
|
Most Likely Time
|
Pessimistic Time
|
|
A
|
3
|
4
|
5
|
--
|
B
|
5
|
7
|
9
|
--
|
C
|
2
|
3
|
10
|
A
|
D
|
2
|
5
|
8
|
B
|
E
|
1
|
7
|
7
|
B
|
F
|
3
|
7
|
9
|
C, D
|
G
|
7
|
8
|
9
|
D, E
|
H
|
4
|
6
|
10
|
F
|
A) Less than or equal to 22 days
B) 23 days
C) 24 days
D) 25 days or more