Earliest completion time for a project


What is the earliest completion time for a project with this information about activities?

Activity

Optimistic Time

Most Likely Time

Pessimistic Time

 

A

3

4

5

 --

B

5

7

9

 --

C

2

3

10

A

D

2

5

8

B

E

1

7

7

B

F

3

7

9

C, D

G

7

8

9

D, E

H

4

6

10

F

A) Less than or equal to 22 days

B) 23 days

C) 24 days

D) 25 days or more