Question - Standard fixed overhead rate for the Dempsey Company is $2 per direct labor hour calculated based on 26,000 hour expected capacity. Actual fixed overhead for the month is $51,350. Each unit requires 2 hours of direct labor. Each unit requires 20 minutes of direct labor. If 13,200 units were produced, what was the fixed overhead spending variance?