Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which must be ready for delivery at the start of week 6. An MRP planner has prepared the following table showing product structure, lead times (orders are lot-for-lot), and quantities on hand:
Deluxe Easter Basket BOM Lead Time On-Hand
Deluxe Easter Basket 1 week 10
Dark Chocolate Truffles (2 per) 2 weeks 30
Carved Chocolate Eggs (4 per) 1 week 50
Each Deluxe Basket contains two dark chocolate truffles and four carved chocolate eggs. If the firm is using a fixed-period lot size of two periods, what is the order size for the first order?