Dweller, Inc. is considering a four-year project that has an initial after-tax outlay or after-tax cost of $80,000. The future cash inflows from its project are $40,000, $40,000, $30,000 and $30,000 for years 1, 2, 3 and 4, respectively. Dweller uses the net present value method and has a discount rate of 12%. Will Dweller accept the project?
A) Dweller rejects the project because the NPV is -$3,021.
B) Dweller accepts the project because the NPV is greater than $28,000.
C) Dweller rejects the project because the NPV is less than -$4,000.
D) Dweller accepts the project because the NPV is greater than $30,000.