Drawing the gantt chart for the project activities


Answer all the questions.

Question1) Depict different phases of programme planning diagrammatically and explain them by taking an suitable example.

Question2) Differentiate between:

(a) PRA and RRA

(b) Project Planning and Project Appraisal

Question3) Describe the procedure for preparing a NREGS plan.

Question4) Describe briefly various functions of management.

Question5) (i) Draw the Gantt chart for the following project activities.

S.No.    Activity                    Time requirement (weeks)

1.    Development of land                                  9
2.    Ploughing and minor leveling                       4
3.    Digging of pits for planting                          5
4.    Purchasing of farm yard manure                 3
5.    Purchasing of plants                                  10
6.    Application of farm yard manure                 2
7.    Transplanting plants                                   2

(ii) Prepare network and give event numbers for the following.

PERT Event        Preceding Event   
Event No. 1        -
Event No. 2        1
Event No. 3        2
Event No. 4        2, 3
Event No. 5        4