Embassy Club Condominium, located on the west coast of Florida, is undetaking a summer renovation of tis main building. The project is scheduled to begin May 1, and a September 1 (17 week) completion date is desired. The condominium manager identified the following renovation activites and their estimated times.
Activity |
Immediate Predecessor |
Time |
A |
|
3 |
B |
|
1 |
C |
|
2 |
D |
A,B,C |
4 |
E |
C,D |
5 |
F |
A |
3 |
G |
D,F |
6 |
H |
E |
4 |
a) Draw a project network.
b) What are the critical activities?
c) What activity has the most slack time?
d) Will the project be completed by September 1?
Your answer must be typed, double-spaced, Times New Roman font (size 12), one-inch margins on all sides, APA format and also include references.