Activity
|
Immediate Predecessor
|
(Time Weeks)
|
A
|
-
|
1
|
B
|
A
|
4
|
C
|
A
|
4
|
D
|
B
|
2
|
E
|
C ,D
|
5
|
F
|
D
|
2
|
G
|
F
|
2
|
H
|
E, G
|
3
|
Draw the project network.
What is the critical path?
How many weeks will it take to complete the project?
Which activities have slack, and how much?
Please show work, I need to know how to do it, Thanks!