The following activities are part of a project to be scheduled using CPM (activity on the arrow):
Activity Time (weeks)
1-2 6
1-3 7
2-3 4
3-4 8
Draw the project network. Calculate the ES, EF, LS, and LF time estimates for each activity and identify the critical path and its duration. Which activities you would consider for crashing?