Draw the precedence diagram with the processing times


Assignment:

Line Balancing

Employees at ABC Assembly Line work from 6am to 2pm Monday through Friday. Everyone on the assembly line is allowed a 30 minute lunch and two 15 minute breaks. Other cross-trained associates cover lunches and breaks for the associates on the assembly line so the line doesn't stop. On your second week at ABC Assembly Line, you record the processes of the assembly line are laid out in the following manner:

Task Predecessor

1 none

2 1

3 none

4 2

5 3

6 4, 5

The intern the summer before recorded the following observations:

Task 1 average cycle time = 1.1 min

Task 2 average cycle time = 0.8 min

Task 5 average cycle time = 1.4 min

You complete the 20 observations at each of the other 3 stations and record the following:

Task 3 average cycle time = 52 sec

Task 4 average cycle time = 36 sec

Task 6 average cycle time = 63 sec

Due to quality issues in the field causing $300k worth of parts to be recalled, a new quality needs to be added after Task 4 and the quality check must be completed before can begin. The Quality Assurance Team estimates this new process will take an average of 27 seconds to complete. Prior to adding this quality check task, the line was achieving an output of 300 units per day and the Plant Manager needs to maintain that output.

Assuming the new quality check task is added, do the following:

a) Draw the precedence diagram with the processing times for each task displayed .

b) Compute the Takt time for the line (1 point).

c) Assign tasks to work stations using the greatest amount of time remaining as a heuristic rule .

d) Compute the efficiency and percent idle time for the system .

e) Determine which work station has the least amount of idle time. Determine which work station has the greatest amount of idle time .

Request for Solution File

Ask an Expert for Answer!!
Other Subject: Draw the precedence diagram with the processing times
Reference No:- TGS01879569

Expected delivery within 24 Hours