The following project data in the dependency table was provided by ABC Ltd IT manager; it relates to a new ICT project to be undertaken.
Activity
|
Duration (Days)
|
PrecedingActivities
|
Start Date
|
A
|
4
|
-
|
1/06/15
|
B
|
7
|
A
|
5/06/15
|
C
|
7
|
A
|
12/6/15
|
D
|
6
|
A
|
19/6/15
|
E
|
2
|
C
|
25/6/15
|
F
|
5
|
C
|
27/6/15
|
G
|
9
|
C
|
02/07/15
|
H
|
6
|
B, E
|
11/07/15
|
J
|
6
|
D, F
|
17/7/15
|
K
|
9
|
H, G, J
|
23/7/15
|
You are required to:
(i) draw the network flow diagram.
ii) Identify the Critical path and its duration.
(iii) Draw Gantt chart to illustrate the project.