Draw the network diagram of the following project according to the activity list and relationships mentioned below
Table 1
|
Activity
|
Duration
|
Dependence
|
Relationships
|
Lag
|
A
|
2
|
-
|
-
|
-
|
B
|
3
|
A
|
SS
|
2
|
C
|
5
|
B
|
FS
|
4
|
D
|
6
|
A
E
|
FS
FS
|
5
3
|
E
|
7
|
A
|
FS
|
2
|
F
|
6
|
C
|
FS
|
2
|
G
|
5
|
F
|
FS
|
0
|
H
|
4
|
C
D
|
FS
FS
|
0
2
|
I
|
5
|
H
G
|
FS
FS
|
0
3
|
J
|
7
|
K
|
FS
|
5
|
K
|
4
|
I
|
FS
|
4
|