Draw the network diagram for the project


Problem:

Activity    Immediate Predecessor(s)    Activity Time (days)
A    -    4
B    -    3
C    -    5
D    A, B    3
E    B    6
F    D, C    4
G    E, C    8
H    F, G    12

a. Draw the network diagram for this project.

b. Specify the critical path.

c. Calculate the slack for activities A and D.

d. What happens to the slack for activity D if A takes five weeks?