1. The following information has been gathered for a project:
a. Draw the network diagram.
b. Calculate the slack for each activity and determine the critical path. How long will the project take?
2. Consider the following information for a project to add a drive-thru window at Crestview Bank.
a. Draw the network diagram for this project
b. Specify the critical path.
a. Calculate the slack for activities A and D.
3. Barbara Gordon, the project manager for Web Ventures, Inc., compiled a table showing time estimates
for each of the activities of a project to upgrade the
company's Web page, including optimistic, most likely, and pessimistic.
a. Calculate the expected time, t1, for each activity.
b. Calculate the variance, cr2, for each activity.
Attachment:- MNG_Question.pdf