Discuss the below in detail:
Q: Table below shows the activities, immediate predecessors and activity durations of a project. Draw the AON project network. How long would it take to complete this project? What is the length of the critical path?
Activity |
Immediate Predecessor(s)
|
Duration (Days)
|
A |
- |
2 |
B |
A |
4 |
C |
A |
4 |
D |
B |
6 |
E |
D |
9 |
F |
C |
8 |
G |
E, F
|
2 |
H |
G |
2 |
I |
G |
3 |
J |
H, I
|
4 |
K |
J |
4 |